Progress Report of Works done till 01-01-2015

JKPCC is a Govt Organization meant for execution of works like Bridges, Buildings, Hospitals etc. This organization has been created in the year 1969 with main objective of construction of major works. At present we have many works being executed in JKPCC in the entire state. The major works like secretariat shopping complex, Flyover, Haj Complex, Revenue complex, LD Hospital etc. In kupwara JKPCC has constructed DC Office Kupwara, Bypass bridge kupwara near DC Office, Court complex, District library, Mughalpora Bridge, Gushi Bridge, Degree College Kupwara, Handwara Hospital, Talri Bridge, TV Tower at Tangdar, TV Tower at Kupwara, Radio station Kupwara and many other structures.

Almost every district has a working unit of JKPCC heeded by a Deputy General Manager with Managers at his Assistance for the execution of projects.

In kupwara unit we have:

 

 

1. Dy. General Manager (EX. Eng)

 

Mr. Mohd Sidiq Malla.

2. Managers.

 

 

i. Mr. Ajaz Ahmad Khan. (AEE)

1. I.P.D. Kupwara

 

2. Dragmulla Hatmulla Bridge.

 

3. Kanthpora Bridge.

 

4. Zangli Bridge.

ii. Mr. Mushtaq Ahmad Dar (AEE)

1. R.E.W. Kupwara.

 

2. Allopathic Dispensary Hyhama.

iii. Mr. Altaf Hussan Lone (AEE)

1. Degree College Tangdar.

 

2. Manzgam Panzgam bride.

 

3. Tumina Chowkibal bridge.

 

4.

Meelyal Bridge.

 

5.

Degree College Kupwara.

 

6. Aloosa Bridge.

iv. Mr. Mohd Amin Ganie (AE)

1. Degree College Sogam.

 

2.

S.D.H. Sogam.

 

3.

Polytechnic College Karihama.

 

4.

S.D.H. Kralpora.

v. Mr. Shahid Saleem. (AE)

1. J.N.V. Putshai.

 

2.

Women’s Degree College Kupwara.

vi. Mr. Rifat Khalid. (JE)

1. Nagree Bridge.

 

2.

P.H.C. Batpora.

 

3.

6 No of Community Centers.

vii.Mr. Manzoor Ah Najar (JE)

viii.Mr. Mushtaq Ah Bulla (JE)

1.Shartwari Bridge.

2.Auditiorum Hanga.

1.I.S.M. Kupwara.

2.Sohipora Bridge.

3.Bohipora Bridge.

4.Poshpora Bridge.

5.Kunan Bridge.

Tumina Chowkibal Bridge Length=260Mtr No of span. 07

Est Cost :

 

829.00

D.O.S :

 

Feb. 01

D.O.C :

 

Sep. 15

F/R by P.A :

 

428.00

Work done :

 

503.00

Balance P.A :

401.00

Head =

State Sector.

Physical Status: -

Sub structure / pier upto cap level completed. Deck slab of 1st span completed. Including stressing cables. Two No's of PSC girder in span 2nd completed, deck slab of 2nd span completed. One No of PSC girder of 3rd span completed and stressing of

1st stage completed.

Manzgam Panzgam bridge Length= 160Mtr No of span. 04

Est Cost :

 

652.00

D.O.S :

 

Feb. 01

D.O.C :

 

Jun. 15

F/R by P.A :

 

548.06

Work done :

 

580.00

Balance P.A :

103.94

Head =

State Sector.

Physical Status: -

Main bridge completed and filling of expansion joints wearing coat and painting. Bridge approach on Manzgam side 60%completed . Bridge approach on Panzgam side about 1200rft's length has not being taken in hand, because the land has not been handed over.

Aloosa Bridge Length= 220Mtr No of span. 06

Est Cost :

684.00

D.O.S :

Mar.10

D.O.C :

Jun.16

F/R by P.A :

83.50

Work done :

123.00

Balance P.A :

600.50

Head =

State Sector.

Physical Status: -

Left abutment completed. Pier P1 & P2 footing raft foundation completed and shaft in progress. Work resumed in pace of slow work.

Zangli Bridge Length= 40Mtr No of Single span.

Est Cost :

 

221.00

D.O.S :

 

Nov.10

D.O.C :

 

Mar.15

F/R by P.A :

 

86.50

Work done :

 

99.00

Balance P.A :

134.50

Head =

State Sector.

Physical Status: -

 

Left abutment completed upto cap level. Right abutment on Zangli side

completed above Nallah bed level. Balance work in progress.

Trehgam bridge Girder bridge No of span. 02.

Est Cost :

750.00

 

 

 

D.O.S :

Dec.10

 

 

 

D.O.C :

Mar.14

 

 

 

F/R by P.A :

475.00

 

 

 

Work done :

455.00

 

 

 

Balance P.A :

275.00

 

 

 

Head =

State Sector.

 

 

 

Physical Status: -

 

 

 

 

Phase 1st 3-

spans

of bridge completed except

wearing coat.

Proposed, additional

two

spans of bridge not taken in

hand due to

land dispute and non availability of funds.

Meelyal Bridge Length= 16Mtr Single span.

Est Cost :

99.00

D.O.S :

Sep.10

D.O.C :

Nov.14

F/R by P.A :

73.00

Work done :

98.00

Balance P.A :

26.00

Head =

State Sector.

Physical Status: -

Sub, structure completed. Super structure completed. Approaches in progress.

Bohipore Bridge Length= 90Mtr No of span. 03.

Est Cost :

 

230.00

D.O.S :

 

Jun.10

D.O.C :

 

Sep.15

F/R by P.A :

 

65.00

Work done :

 

47.00

Balance P.A :

165.00

Head =

State Sector.

Physical Status: -

 

Left abutment A1 completed upto cap level. Pier P1 completed upto

ground level. Pier P2 completed upto ground level. Abutment A2 not started yet.

Kunan Bridge Length= 120Mtr No of span. 03.

Est Cost :

543.00

D.O.S :

Jun. 10

D.O.C :

Jun. 16

F/R by P.A :

68.00

Work done :

76.00

Balance P.A :

475.00

Head =

State Sector.

Physical Status: -

 

Left abutment raised upto ground level. Shaft work was in progress Pier P1

raised upto cap level. Approach on Kunan side completed 40%. work stopped due to non availablity of funds.

Shartwari Bridge Length= 130Mtr span 04.

Est Cost :

271.00

D.O.S :

Sep.11

D.O.C :

Oct.15

F/R by P.A :

33.00

Work done :

68.00

Balance P.A :

238.00

Head =

State Sector.

Physical Status: -

Hutments completed, Pier P1 completed above ground level. Approach road is in progress from Shartwari side. Abutment A1 completed upto ground level. Pier P2 in progress.work stopped

due to non availablity of funds.

Kanthpora Bridge Length= 92Mtr span 02.

Est Cost :

411.00

D.O.S :

Nov.10

D.O.C :

Jan.15

F/R by P.A :

49.51

Work done :

80.00

Balance P.A :

361.49

Head =

State Sector.

Physical Status: -

 

Right abutment completed upto cap level. Pier P1 completed upto cap

level. Abutment A2 in progress. Work stopped due to Non- availability of funds.

Lecture Block Degree College Kupwara Plinth area=684sqm No of

 

story. 02.

Est Cost :

340.84

D.O.S :

Dec.09

D.O.C :

Dec.14

F/R by P.A :

299.70

Work done :

299.70

Balance P.A :

41.14

Head =

State Sector.

Physical Status: -

Building completed, Finishing items in progress.

Degree College Sogam Plinth area=1367sqm No of story. 02 .

Est Cost :

1304.00

D.O.S :

Jan.11

D.O.C :

Jul.15

F/R by P.A :

800.00

Work done :

790.00

Balance P.A :

504.00

Head =

State Sector.

Physical Status: -

Ground floor completed including brick work. First floor 80% structure with slab completed. Balance work in progress.

Degree College Tangdar Plinth area=1367sqm No of story. 02 .

Est Cost :

1550.00

D.O.S :

Jan.11

D.O.C :

May.15

F/R by P.A :

693.00

Work done :

792.00

Balance P.A :

857.20

Head =

State Sector.

Physical Status: -

Ground floor and first floor including brick work complete. Truss work complete. Finishing work in progress.

R.E.W. Kupwara Plinth area= 2914sft No of story. 02.

Est Cost :

237.50

D.O.S :

Dec.02

D.O.C :

Sep.14

F/R by P.A :

118.00

Work done :

166.00

Balance P.A :

119.50

Head =

State Sector.

Physical Status: -

Main building structure completed upto 1st floor including slab. Second floor column in progress.

Dragmulla Bridge Length=110Mtr No of span. 03

Est Cost :

364

D.O.S :

Jun. 11

D.O.C :

Oct. 14

F/R by P.A :

281.52

Work done :

200.00

Balance with P.A : - 82.48

Head =

NABARD.

Physical Status: -

1. Both abutment on Hatmulla & Dragmulla side completed. 2. Pier P1 and P2 completed. Part super structure material is dumped at site but

due to stay order of Hon’ble Court work is stopped till further decisions.

Sohipore Bridge Length= 24Mtr Single span.

Est Cost :

107.67

D.O.S :

Sep.10

D.O.C :

Mar.15

F/R by P.A :

66.66

Work done :

81.00

Balance P.A :

41.01

Head =

NABARD.

Physical Status: -

Left abutment completed upto cap level. Right abutment completed

upto cap level. Approach work in progress.

Nagree Bridge Length= 173Mtr span 05.

Est Cost :

599.00

D.O.S :

Aug.10

D.O.C :

Oct.15

F/R by P.A :

422.13

Work done :

360.00

Balance P.A :

176.87

Head =

NABARD.

Physical Status: -

 

Left abutment completed upto cap level. Right abutment completed upto cap level. Pier P1, P2, P3 and P4, completed upto cap level. approach work on both sides is in progress. Super structure work of the bridge is in progress by way of making of plate girder.

Allopathic Dispensary Hyhama Plinth area= 2307Sft. No of story. 02.

Est Cost :

147.31

D.O.S :

Jul:10

D.O.C :

Nov.14

F/R by P.A :

125.47

Work done :

125.47

Balance P.A :

21.84

Head =

NABARD.

Physical Status: -

 

 

Plaster ground floor and first floor in progress.

Poshpora bridge Length= 120Mtr No of span. 3x40.

Estimated Cost =

562.00

D.O.S =

Jan. 05

D.O.C =

Jun. 15

F/R by P.A =

267.45

Work done =

310.00

Balance with P.A =

252.00

Head = B.R.G.F/R.S.V.Y.

Physical Status: -

Abutment A1 of Poshpora side completed upto cap and approach wall and road in progress. Pier P1 shaft work completed including cap. Pier P2 shaft work complete including cap. Abutment A2 shaft upto ground level completed.

Auditorium Hanga Plinth area= 9300Sqm No of story. 1.50.

Est Cost :

358.21

D.O.S :

Jun:10

D.O.C :

Sep.14

F/R by P.A :

193.56

Work done :

218.00

Balance P.A :

164.65

Head =

BRGF/BADP.

Physical Status: -

Main building structure completed upto truss level including slab. 70% brick work and plaster completed. Rest finishing work in progress.

Polytechnic College Karihama Plinth area=2900sqm No of story. 02 .

Est Cost :

1862.32

D.O.S :

Oct.11

D.O.C :

Dec.16

F/R by P.A :

800.00

Work done :

830.00

Balance P.A :

1062.32

Head =

C.S.S.

Physical Status: -

 

85% ground floor completed including brick work. 50% first floor slab completed. Balance work of first floor slab work in progress.

Women’s Degree College Sulkoot Kupwara.

Est Cost :

1083.70

D.O.S :

Mar.14

D.O.C :

 

F/R by P.A :

200.00

Work done :

70.00

Balance P.A :

883.70

Head =

C. S. S.

Physical Status: -

 

Main building (excavation complete, mud mate laid, raft foundation 95% complete work on foundation columns in progress. Approach road to the site complete.

Community Centre Sheikhpora.

Est Cost :

39.00

D.O.S :

Jun:10

D.O.C :

Sep.14

F/R by P.A :

38.80

Work done :

34.00

Balance P.A :

0.20

Head =

District Plan.

Physical Status: -

Building roofed with CGI over steel trusses. Finishing items in

progress.

Community Centre Wajhama.

Est Cost :

39.00

D.O.S :

Jun:10

D.O.C :

Sep.14

F/R by P.A :

38.00

Work done :

34.90

Balance P.A :

0.20

Head =

District Plan.

Physical Status: -

Building roofed with CGI over steel trusses. Finishing items in

progress.

Community Centre Hampora.

Est Cost :

39.00

D.O.S :

Jun:10

D.O.C :

Sep.14

F/R by P.A :

38.80

Work done :

35.39

Balance P.A :

0.20

Head =

District Plan.

Physical Status: -

Building roofed with CGI over steel trusses. Finishing items in

progress.

Community Centre Mawer Payeen.

Est Cost :

39.00

D.O.S :

Jun:10

D.O.C :

Sep.14

F/R by P.A :

38.80

Work done :

36.00

Balance P.A :

0.20

Head =

District Plan.

Physical Status: -

Building roofed with CGI over steel trusses. Finishing items in

progress.